Q3 FY2024 Highlights
-
-
-
-
-
-
-
-
Snapshot: Delorean was focussed on project delivery and activities aimed at bringing its next four
bioenergy infrastructure projects to final investment decision (FID). These activities are underpinning
the Company’s future growth trajectory, ensuring sustained momentum and value creation.
Yarra Valley Water: In Q3 FY2024 construction works continued on the $53m Yarra Valley Water food
waste to energy project with earthworks and civils well underway on site and plant items in
fabrication.
SA1 and VIC1 Projects: Delorean is working with a shortlist of potential investors to close out a
platform of project finance for the SA1 and VIC1 projects (investment circa $60m). The undertaking of
these build/own/operate projects remains subject to completion of this diligence and the FID being
made to proceed.
Brickworks/NSW1 Project: The ongoing co-development of the NSW1 project, in a landmark
collaboration with Brickworks Building Products, saw significant progress in Q3 FY2024. The Company
has been actively preparing comprehensive documentation for full development approval, expected
in Q4 FY2024.
QLD1 Project: Delorean was awarded a $5,000,000 grant under the Queensland Government’s
Resource Recovery Industry Development Program to be applied towards the construction,
commissioning, and operation of Delorean’s QLD 1 bioenergy facility project.
ATCO MOU: Delorean entered into a landmark collaboration agreement with ATCO Gas Australia Pty
Ltd. Under the Memorandum of Understanding (MOU), DEL and ATCO have agreed to work together
to connect Delorean’s bioenergy projects to ATCO’s gas networks to enable the supply of biomethane
to help fulfill ATCO’s obligations for Unaccounted For Gas.
R&D Refund: Following quarter end, Delorean received its R&D tax refund from the ATO, in respect
of the year to 30 June 2023, totalling $291,871, for research and development work completed on
previous projects, building DEL’s intellectual property and design for future bioenergy projects.
LGC Shortfall Refund: Subsequent to quarter end, Delorean Energy Retail received its first refund of
historic LGC shortfall charges, totalling $1,599,154.
Renewable Gas Demand: Significant ongoing demand from both government and business sectors for
Delorean’s renewable gas (biomethane) product in a market where renewable gas is scarce.
Cash Balance: Current cash balance of $6.8m as at 31 March 2024.
Image 1: QLD1 Bioenergy Project Render
DELOREAN CORPORATION LIMITED | QUARTERLY ACTIVITIES REPORT 31 MARCH 2024
2
Q2 FY2024 Activities Report
Delorean Corporation Limited (ASX:DEL) is pleased to provide an overview of the March 2024 quarter (Q3
FY2024) activities and the associated cash flows and cash position in the Appendix 4C (attached).
Business Overview
Delorean Corporation is a vertically integrated business operating in two high growth investment sectors –
renewable energy and waste management. Delorean is pioneering the Australian market with bioenergy and
driving commercial production of mains-grade renewable gas. Delorean has the inhouse capability to deliver
bioenergy projects across the full lifecycle, from project conception to completion; processing organic waste
and generating and monetising renewable electricity, heat and gas.
The core focus of the business is to develop, construct, own and operate bioenergy infrastructure in Australia.
Revenue is derived from the acceptance of organic waste and agricultural residues, the generation of
renewable electricity and the production of renewable natural gas.
The business comprises three interoperable divisions:
•
Infrastructure (core): rollout of Delorean owned bioenergy projects through partnerships.
•
Engineering: refocused to primarily support EPC and O&M of Delorean’s own projects whilst selectively
taking on third party work
•
Energy Retail (inactive): Delorean retains licenses for retailing of energy (electricity and gas) generated only
from Delorean projects.
DELOREAN CORPORATION LIMITED | QUARTERLY ACTIVITIES REPORT 31 MARCH 2024
3
Investment Highlights
✓ Unique and proven track record of delivering award-winning, innovative and successful Australasian
bioenergy projects
Image 4: Jandakot Bioenergy Project
✓ Strong pipeline of bioenergy projects under development to capitalise on the growth of Australian
bioenergy market
✓ A leading force in advancing Australia’s bioenergy sector and providing unique solutions to address
especially hard to abate sectors
✓ Strong ESG credentials with TCFD and global ESG standards alignment, and formal sustainability reporting
✓ Ideally positioned to capitalise on the national drive towards zero organic waste to landfill and
decarbonisation of energy
Project Pipeline
The following graphic sets out an overview of Delorean projects, completed, under construction, under
development and in the pipeline.
Delorean has successfully delivered 3 award-winning bioenergy projects (Jandakot WA, Blue Lake Milling SA,
Ecogas NZ) and is now in construction of its fourth and biggest project for Yarra Valley Water. Delorean’s pipeline
of works will see Delorean delivering a greater number of projects of larger scale, consistent with the growth in
Australia’s bioenergy sector.
Image 2: Delorean Corporation Project Pipeline
DELOREAN CORPORATION LIMITED | QUARTERLY ACTIVITIES REPORT 31 MARCH 2024
4
Delorean Engineering Division
Delorean’s Engineering Division delivers engineering design, construction and operation/maintenance services
for third parties under contract, and for Delorean Infrastructure Division’s build/own/operate projects.
During the quarter, Delorean’s Engineering Division was primarily focussed on:
•
Commencement of site works and construction of Yarra Valley Water’s Lilydale facility, with major
earthwork and civils works underway on site and plant items in fabrication.
•
Supporting the submission of Environmental Impact Statements and Development Application for the
Brickworks Project (NSW1) by Delorean Infrastructure Division.
•
Operational support for Blue Lake Milling and Ecogas Bioenergy facilities previously constructed by
Delorean and now in operation.
Yarra Valley Water, VIC Bioenergy Plant
Project Background
Location: Lilydale, Victoria – circa $53m + $6.5m O&M contract value
Project Update
Following the receipt of final regulatory and development approvals, site works are now underway as the
project enters the full construction phase. Initial excavation of the Waste to Energy plant slab has finished and
the access road has been commenced. Notable visitors to site include the State Minister for Water the
Honourable Harriet Shing and Yarra Ranges Council Mayor Sophie Todorov.
Image 3 & 4: Yarra Valley Water site works
Image 5 & 6: Yarra Valley Water Bioenergy Plant ministerial visit event
DELOREAN CORPORATION LIMITED | QUARTERLY ACTIVITIES REPORT 31 MARCH 2024
5
Delorean Infrastructure Division
Delorean’s Infrastructure Division is responsible for development, ownership and operation of commercialscale anaerobic digestion bioenergy facilities in Australia.
During the quarter, Delorean’s Infrastructure Division was predominantly focussed on:
•
Completing submission of Environmental Impact Statements and Development Application for the
Brickworks Project (NSW1).
•
Development and due diligence activities on the Company’s VIC1 and SA1 projects
•
QLD1 completing design and environment and regulatory compliance for development approval
•
Ongoing development of Delorean’s infrastructure project pipeline
Brickworks Bioenergy Project Development
Project Update
In Q3 FY2024, Brickworks Building Products and Delorean continued to progress the Development Stage of the
NSW1 project under a Master Services Agreement (MSA). The Company has been actively preparing a
comprehensive documentation for full development approval, expected in Q4 FY2024.
Image 7: NSW1 Bioenergy Plant Render
DELOREAN CORPORATION LIMITED | QUARTERLY ACTIVITIES REPORT 31 MARCH 2024
6
SA1 and VIC1 Project Development
During Q3 FY2024, Delorean was actively working with a shortlist of potential investors with the objective of
securing a strategic investment partner for the SA1 and VIC 1 projects.
Both projects are shovel ready for full construction pending project finance.
Image 8: VIC1 Bioenergy Plant Render
Image 9: SA1 Bioenergy Plant Render
Delorean Infrastructure Project Pipeline Development
During Q3 FY2024, Delorean continued the active development of its bioenergy infrastructure project pipeline.
Beyond the SA1, VIC1 and NSW1 projects, the most advanced of these projects is the QLD1 Bioenergy Plant.
In Q3 FY2024, Delorean was awarded a $5,000,000 grant under the Queensland Government’s Resource
Recovery Industry Development Program to be applied towards the construction, commissioning, and
operation of Delorean’s QLD 1 bioenergy facility project.
The Company is currently preparing to progress the project from feasibility stage to development approval.
The project is expected to be FID-ready by late CY2024.
Delorean Energy Retail Division
Delorean’s Energy Retail Division is currently inactive, pending a future scale up of its retail operations as
Delorean’s Infrastructure assets come onstream.
Delorean intends to retain its WA and National retail electricity and Victorian Gas licenses on an ongoing basis
in support of the Company’s rollout of bioenergy infrastructure across Australia.
During this quarter, Delorean Energy Retail acquired 24,248 Large Scale Generation certificates (LGCs) at
$46.50 per LGC, for surrender to the Clean Energy Regulator (CER) as part of Delorean’s ongoing LGC strategy
(announced to the ASX on 31 July 2023). The surrender of these LGCs unlocked the shortfall charge paid by
Delorean to CER in respect of the 2020 calendar year, allowing $1,599,154 to be refunded back to the
Company. These funds were utilised to repay Roadnight Capital, Delorean’s funding partner for this strategy.
DELOREAN CORPORATION LIMITED | QUARTERLY ACTIVITIES REPORT 31 MARCH 2024
7
Delorean Corporate
Subsequent to quarter end, Delorean’s Corporate Division received a refund of $291,781 from the Australian
Taxation Office (ATO). This refund is Delorean’s R&D tax incentive offset for the year ended 30 June 2023,
reimbursing a proportion of the R&D costs incurred by the Group in that year.
As a Group, Delorean undertakes a variety of research and development activities as it develops new
techniques for use in its Anaerobic Digestion plants. Receipt of this refund will support our continued work in
this space.
Environment, Social and Governance
Delorean remains proud to be advancing its commitment to sustainability. In October 2023, Delorean
published its second annual ESG Report.
This report provides our stakeholders a comprehensive analysis of the Group’s Environmental, Social and
Governance (ESG) performance, highlighting key sustainability milestones achieved during the Financial Year
2023. Additionally, it offers an update on our continued progress towards future sustainability goals.
Planned Activity – Q4 FY2024
In Q4 FY2024, Delorean’s focus is in the following key areas:
•
•
•
•
Select a preferred Infrastructure Projects Investor towards moving Delorean’s SA1 and VIC1 projects
into construction.
Continue progress with NSW1 project through next stages following submission of Development
Application, including work on detailed commercial terms and project finance options with
Brickworks, to bring the project to a point where it is FID-ready.
Progress from siteworks through to full construction on Delorean Engineering’s Yarra Valley Water
project.
Progress the development of its QLD1 project.
DELOREAN CORPORATION LIMITED | QUARTERLY ACTIVITIES REPORT 31 MARCH 2024
8
Additional Appendix 4C Disclosures
The following information is provided as required under ASX Listing Rule 4.7C that has not been disclosed in
the body of the quarterly activities report.
Summary of Expenditure incurred on Projects
A summary of expenditure incurred in AUD excluding GST (accruals basis) for the quarter on our key projects
and cost centres is as follows:
•
•
•
•
•
•
•
Ecogas - $Nil
Yarra Valley Water - $6,528k
Brickworks - $153k
South Australia One and Victoria One - $3k
Energy Retail - $1,207k
Operations & Maintenance - $29k
Overheads - $783k
Payments made to Related Parties
Payments totalling $170k made to related parties and their associates are for director salaries and
superannuation of $19k and payments for corporate services of $19k. All payments were on normal
commercial terms.
DELOREAN CORPORATION LIMITED | QUARTERLY ACTIVITIES REPORT 31 MARCH 2024
9
Disclaimer
This report has been prepared by Delorean Corporation Limited (Delorean). The material contained in this
report is for information purposes only. This release is not an offer or invitation for subscription or purchase
of, or a recommendation in relation to, securities in Delorean and neither this release nor anything contained
in it shall form the basis of any contract or commitment.
This report may contain forward-looking statements. Forward-looking statements include, but are not limited
to, statements concerning Delorean business plans, intentions, opportunities, expectations, capabilities, and
other statements that are not historical facts. Forward-looking statements include those containing such
words as could, plan, target, estimate, forecast, anticipate, indicate, expect, intend, may, potential, should or
similar expressions. Such forward-looking statements are not guarantees of future performance and involve
known and unknown risks, uncertainties, assumptions, and other important factors, many of which are beyond
the control of Delorean, and which could cause actual results to differ from those expressed in this report.
Because actual results might differ materially to the information in this report, Delorean does not make, and
this report should not be relied upon as, any representation or warranty as to the accuracy, or reasonableness,
of the underlying assumptions and uncertainties. Investors are cautioned to view all forward-looking
statements with caution and to not place undue reliance on such statements.
The report has been prepared by Delorean based on information available to it, including information from
third parties, and has not been independently verified. No representation or warranty, express or implied, is
made to the fairness, accuracy or completeness of the information or opinions contained in this report.
About Delorean Corporation Ltd (ASX:DEL)
Shares in Delorean Corporation Limited (ASX: DEL) are traded on the Australian Securities Exchange (ASX).
For more information, please visit our website: www.deloreancorporation.com.au
DELOREAN CORPORATION LIMITED | QUARTERLY ACTIVITIES REPORT 31 MARCH 2024
10
Rule 4.7B
Appendix 4C
Quarterly cash flow report for entities
subject to Listing Rule 4.7B
Name of entity
Delorean Corporation Limited
ABN
Quarter ended (“current quarter”)
62 638 111 127
31/03/2024
Consolidated statement of cash flows
Current quarter
$A’000
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
Year to date (9
months)
$A’000
5,656
17,607
-
-
(3,018)
(9,225)
advertising and marketing
(2)
(2)
leased assets
(22)
(66)
staff costs
(885)
(2,440)
administration and corporate costs
(869)
(2,773)
research and development
product manufacturing and operating costs
1.3
Dividends received (see note 3)
-
-
1.4
Interest received
1
1
1.5
Interest and other costs of finance paid
(71)
(215)
1.6
Income taxes paid
-
-
1.7
Government grants and tax incentives
-
4
1.8
Other (provide details if material)
-
-
1.9
Net cash from / (used in) operating
activities
790
2,891
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
(a) Entities
-
-
businesses
-
-
property, plant and equipment
-
(176)
investments
-
-
intellectual property
-
-
ASX Listing Rules Appendix 4C (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 11
Appendix 4C
Quarterly cash flow report for entities subject to Listing Rule 4.7B
Consolidated statement of cash flows
Current quarter
$A’000
Year to date (9
months)
$A’000
other non-current assets
2.2
Proceeds from disposal of:
(a) entities
-
-
businesses
-
73
property, plant and equipment
-
31
investments
-
-
intellectual property
-
-
other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received (see note 3)
-
-
2.5
Other (provide details if material)
-
-
2.6
Net cash from / (used in) investing
activities
-
(72)
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
-
-
3.2
Proceeds from issue of convertible debt
securities
-
-
3.3
Proceeds from exercise of options
-
-
3.4
Transaction costs related to issues of
equity securities or convertible debt
securities
-
(113)
3.5
Proceeds from borrowings
1,188
3,400
3.6
Repayment of borrowings
(42)
(296)
3.7
Transaction costs related to loans and
borrowings
-
-
3.8
Dividends paid
-
-
3.9
Other (provide details if material)
-
-
3.10
Net cash from / (used in) financing
activities
1,146
2,991
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
4,878
1,004
790
2,891
-
(72)
4.2
Net cash from / (used in) operating
activities (item 1.9 above)
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
ASX Listing Rules Appendix 4C (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 12
Appendix 4C
Quarterly cash flow report for entities subject to Listing Rule 4.7B
Consolidated statement of cash flows
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
4.5
Effect of movement in exchange rates on
cash held
4.6
Cash and cash equivalents at end of
period
5.
Reconciliation of cash and cash
equivalents
Current quarter
$A’000
Year to date (9
months)
$A’000
1,146
2,991
-
-
6,814
6,814
Current quarter
$A’000
Previous quarter
$A’000
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
5.1
Bank balances
2,660
3,418
5.2
Call deposits
-
-
5.3
Bank overdrafts
-
-
5.4
Other (term deposits as security for CBA
bank guarantees)
4,154
1,460
5.5
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
6,814
4,878
6.
Payments to related parties of the entity and their
associates
6.1
Aggregate amount of payments to related parties and their
associates included in item 1
208
6.2
Aggregate amount of payments to related parties and their
associates included in item 2
-
Current quarter
$A'000
Payments for directors’ salaries and superannuation of $189k.
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
ASX Listing Rules Appendix 4C (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 13
Appendix 4C
Quarterly cash flow report for entities subject to Listing Rule 4.7B
7.
Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
7.1
Loan facilities
7.2
Credit standby arrangements
7.3
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
-
-
10
-
Other (please specify)
8,400
8,400
7.4
Total financing facilities
8,410
8,400
7.5
Unused financing facilities available at quarter end
7.6
Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
10
•
Unsecured CBA Credit Cards (17.99% interest rate), no maturity date
•
Convertible note subscription of $5,000,000 from Palisade Impact received in 2
tranches (refer ASX Announcements on 19 October 2022 and 29 December 2022)
•
Corporate debt facility of $3,400,000 from Roadnight Capital, received in two
tranches in July 2023 and January 2024. This facility is linked to the Group’s LGC
strategy (refer ASX Announcement on 31 July 2023). The first shortfall refund of
$1,599,154 under this strategy was received from the Clean Energy Regulator in April
2024, reducing the amount drawn on the facility to $1,800,846.
Not included in the above balances are equipment finance, insurance premium funding
finance and bank guarantee facilities as they are not available to draw for working capital
requirements.
No additional financing facilities have been entered into after quarter end.
(a)
8.
Estimated cash available for future operating activities
$A’000
8.1
Net cash from / (used in) operating activities (item 1.9)
790
8.2
Cash and cash equivalents at quarter end (item 4.6)
6,814
8.3
Unused finance facilities available at quarter end (item 7.5)
8.4
Total available funding (item 8.2 + item 8.3)
8.5
Estimated quarters of funding available (item 8.4 divided by
item 8.1)
10
6,824
N/A
Note: if the entity has reported positive net operating cash flows in item 1.9, answer item 8.5 as “N/A”. Otherwise, a
figure for the estimated quarters of funding available must be included in item 8.5.
8.6
If item 8.5 is less than 2 quarters, please provide answers to the following questions:
8.6.1
Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: N/A
8.6.2
Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: N/A
ASX Listing Rules Appendix 4C (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 14
Appendix 4C
Quarterly cash flow report for entities subject to Listing Rule 4.7B
8.6.3
Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: N/A
Note: where item 8.5 is less than 2 quarters, all of questions 8.6.1, 8.6.2 and 8.6.3 above must be answered.
Compliance statement
1
This statement has been prepared in accordance with accounting standards and policies
which comply with Listing Rule 19.11A.
2
This statement gives a true and fair view of the matters disclosed.
Date:
30 April 2024
Authorised by: By the Board
Notes
1.
This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An
entity that wishes to disclose additional information over and above the minimum required under the Listing Rules is
encouraged to do so.
2.
If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions
in, and provisions of, AASB 107: Statement of Cash Flows apply to this report. If this quarterly cash flow report has been
prepared in accordance with other accounting standards agreed by ASX pursuant to Listing Rule 19.11A, the
corresponding equivalent standard applies to this report.
3.
Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities,
depending on the accounting policy of the entity.
4.
If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”.
If it has been authorised for release to the market by a committee of your board of directors, you can insert here: “By the
[name of board committee – eg Audit and Risk Committee]”. If it has been authorised for release to the market by a
disclosure committee, you can insert here: “By the Disclosure Committee”.
5.
If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as
complying with recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles and
Recommendations, the board should have received a declaration from its CEO and CFO that, in their opinion, the financial
records of the entity have been properly maintained, that this report complies with the appropriate accounting standards
and gives a true and fair view of the cash flows of the entity, and that their opinion has been formed on the basis of a
sound system of risk management and internal control which is operating effectively.
ASX Listing Rules Appendix 4C (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 15
Share your feedback
Discover