Q4 FY25 Quarterly Activities Report
Released
Released
Announcement PDF
Australia’s future in bioenergy and renewables
Company
Update
for the quarter ended
30 June 2025
2025
Delorean Corporation Limited
ACN 638 111 127
Q4 FY2025 Highlights
-
-
-
-
Snapshot: The financial year 2025 finished as a pivotal year for Delorean, with its transition
to renewable gas production and sustainable infrastructure ownership and operation now
well underway. The final quarter saw timely regulatory reforms to further support
Delorean’s projects and strategy. Progress continued across all Delorean’s projects, led by
the Company’s flagship build/own/operate SA1 Salisbury Bioenergy facility which will
deliver renewable biomethane in to the gas network.
Cash Balance: $10.6 million as at 30 June 2025.
Receipts from Customers: $5.8 million for the quarter ended 30 June 2025.
Yarra Valley Water: Construction reached a major milestone on the $59.5 million Yarra
Valley Water Food Waste to Energy Design Build Operate Maintain (DBOM) project, with all
civil, structural, and equipment installation works now complete. Final mechanical and
electrical connections are progressing, and the site is being readied for integrated system
testing and commissioning.
SA1 Salisbury: Delorean’s landmark first Build-Own-Operate asset is progressing strongly,
with major earthworks complete and civil works advancing on schedule. SA1 is a major
milestone, driving long-term shareholder value through renewable gas infrastructure
ownership.
NSW1 Brickworks Project: In Q4 FY2025, Delorean and Brickworks Building Products Pty
Ltd (Brickworks) continued to advance development of the NSW1 Bioenergy Project to
confirm the viability of constructing and operating a renewable energy facility that converts
food waste to biomethane for use in the Brickworks manufacturing plant at Horsley Park,
NSW. A major project milestone was reached on 19 July 2025 with the successful granting
of Development Approval to build and operate this facility.
Renewable Gas: Delorean is ideally positioned to benefit from recent landmark regulatory
reforms announced in Q4 FY2025, including amendments to the NGER Scheme and the
release of AS 4564:2025. These changes formally recognise biomethane as a natural gas
equivalent and enable companies to use Renewable Gas Guarantee of Origin (RGGO)
certificates for injected biomethane to reduce their Scope 1 emissions. These reforms
provide long-awaited certainty, reduce investment risk, and support accelerated
commercial project rollout. This is a potential additional revenue stream for Delorean.
Image 1: YVW Bioenergy Project
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 30 JUNE 2025
2
Q4 FY2025 Activities Report
Delorean Corporation Limited (ASX: DEL) is pleased to provide an overview of the June
2025 quarter (Q4 FY2025) activities and the cash position.
Business Overview
Delorean Corporation is a vertically integrated business operating in two high growth investment
sectors – renewable energy and waste management. Delorean is leading the Australian market
with bioenergy and driving commercial production of mains-grade renewable gas. Delorean has
the inhouse capability to deliver bioenergy projects across the full lifecycle, from project
conception to completion; processing organic waste and generating and monetising renewable
electricity, heat and gas.
The core focus of the business is to develop, construct, own and operate bioenergy infrastructure
in Australia. Revenue is derived from the acceptance of organic waste and agricultural residues
(gate fees), the generation of renewable electricity and the production of renewable gas
(biomethane). Additional revenues are also available from the production of a bi-product,
renewable food grade liquid CO2 (biogenic LCO2) as well as Australian Carbon Credit Units
(ACCUs) and Renewable Gas Guarantees of Origin (RGGOs). Furthermore, there are prospects for
other revenue streams in the future, including the sale of liquid and solid biofertilisers. All these
monetisation streams contribute to the overall financial viability and sustainability of bioenergy
operations.
The business comprises three interoperable divisions:
•
Infrastructure (core): rollout of Delorean owned bioenergy infrastructure through our project
•
pipeline and key partnerships
•
supporting the Bioenergy sector with third party projects and partnerships
Engineering: supporting the EPC and O&M of Delorean’s own projects, while selectively
Energy Retail: retailing of renewable energy (electricity and gas) generated from Delorean
projects through our National electricity retail licence and Victorian Gas retail licence
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 30 JUNE 2025
3
Investment Highlights
Unique high yielding investment opportunity in the bioenergy sector
Delorean is the only Build-Own-Operate (BOO) Bioenergy developer in Australia with a strong
track record of delivering successful award-winning projects across ANZ
Delorean is uniquely positioned to develop its strategic portfolio of BOO projects with
significant industry partners
Long-term value upside
High margin business with contracted multiple revenue flows – predictable and stable income
once assets are operational, underpinned by long-term contracts and attractive project
economics
Unique proposition on the ASX providing equity exposure to shovel ready waste and clean
energy infrastructure projects that demonstrate significant project-level IRRs
Attractive industry dynamics with strong growth potential
Bioenergy industry has significant ‘green’ tailwinds driven by demand for renewable energy
production and waste diversion
Use of organic waste to create gas enables sale of gas at a ‘green’ premium and at a time of
significant natural gas undersupply
Project Pipeline
Delorean has successfully delivered 3 award-winning bioenergy projects (Jandakot WA, Blue Lake
Milling SA, Ecogas NZ) and is currently finalising construction of its largest project to date for Yarra
Valley Water in Lilydale, Victoria, as well as building its first Build-Own-Operate facility, the SA1
Salisbury Bioenergy in South Australia. Delorean’s project pipeline will see Delorean delivering a
more projects at a larger scale across Australia, driving Australia’s growth in the bioenergy sector.
The following graphic sets out an overview of Delorean projects, completed, under construction,
under development and in the pipeline.
Image 2: Delorean Corporation Project Portfolio
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 30 JUNE 2025
4
Delorean Engineering Division
Delorean’s Engineering Division delivers engineering design, construction and
operation/maintenance services for third parties under contract, and for Delorean Infrastructure
Division’s build/own/operate (BOO) projects.
During the quarter, Delorean’s Engineering Division was primarily focussed on:
•
Construction of Yarra Valley Water’s Lilydale facility. All process, mechanical and electrical
equipment are installed, with final connections being made. Testing and commissioning will
•
shortly be underway.
•
supported by the Delorean Infrastructure Division.
Brickworks (NSW1) Bioenergy project Development Application approval which was
Construction of SA1 civil works, which is well underway, with major earthworks now
completed. The reception shed has arrived on site, and all long-lead items have been
procured with key suppliers. The project remains on track to achieve waste acceptance and
•
first gas in 2026
•
and QLD1.
Engineering Design and regulatory support for the Delorean infrastructure projects VIC1
Operational support ongoing for Blue Lake Milling and Ecogas Bioenergy facilities
previously constructed by Delorean.
Yarra Valley Water, VIC Bioenergy Plant
Project Background
Location: Lilydale, Victoria – circa $59.5m total Design Build Operate Maintain contract value
Project Update
All civil, structural, and equipment installation work has been completed. Final mechanical and
electrical connections are in progress, and the site is being prepared for full system testing.
The site has completed over 60,000 hours without injury or lost time incidents (LTI’s).
Image 3 & 4: YVW Bioenergy Plant construction
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 30 JUNE 2025
5
Delorean Infrastructure Division
Delorean’s Infrastructure Division is responsible for development, ownership and operation of
commercial-scale anaerobic digestion bioenergy facilities in Australia.
During the quarter, Delorean’s Infrastructure Division was predominantly focussed on:
•
Advancing the development approval and feasibility study of the NSW1 Bioenergy Project
to ascertain the viability of constructing and operating a renewable energy facility that
converts food waste to biomethane for use in the Brickworks manufacturing plant at
•
•
Horsley Park, NSW.
Feedstock revenues for SA1.
Investment due diligence of QLD1 project.
SA1 Salisbury Bioenergy
Project Update
Civil works are progressing well, with major earthworks completed. The reception shed and
weighbridge have arrived on site and installation will commence shortly. Other major equipment
items have progressed further through the procurement and logistics process.
Image 5: SA1 Salisbury Bioenergy Render
Image 6 - 8: SA1 Salisbury Bioenergy site works
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 30 JUNE 2025
6
NSW1 Brickworks Bioenergy
Project Update
In Q4 FY2025, Delorean and Brickworks Building Products Pty Ltd (Brickworks) continued to
advance the feasibility study of the NSW1 Bioenergy Project to ascertain the viability of
constructing and operating a renewable energy facility that converts food waste to biomethane
for use in the Brickworks manufacturing plant at Horsley Park, NSW.
A major project milestone was reached on 19 July 2025 with the successful granting of
Development Approval to build and operate this facility. The project is now progressing toward a
final investment decision, with a focus on assessing project investment hurdles, securing longform offtake agreements, and negotiating joint venture and facility construction and operation
agreements. A final investment decision on project feasibility is expected to be made by the board
of directors of Brickworks and Delorean in 1HFY2026.
While the parties have agreed to continue to work together on this project, it is subject to Board
approval by each party and binding legal documentation being executed. There can be no
assurance that this project will proceed.
Image 9 & 10: NSW1 Bioenergy Plant Render
VIC1 Stanhope Bioenergy
Further activities were undertaken in sourcing finance to fund construction of the project.
Delorean’s CEO and COO visited the site during the quarter.
Image 11: VIC1 Bioenergy Plant Render
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 30 JUNE 2025
7
Delorean Infrastructure Project Portfolio Development
Delorean continued to work on its medium and long term project pipeline of bioenergy
infrastructure projects. The QLD1 Bioenergy Plant is the project closest to being shovel ready.
Delorean Energy Retail Division
Delorean’s Energy Retail Division stands ready for a strategic scale up of its retail operations when
Delorean’s Infrastructure assets come onstream. Delorean continues to retain its WA and National
retail electricity and Victorian Gas licenses in support of the Company’s future rollout of bioenergy
infrastructure across Australia.
Delorean Corporate
Environment, Social and Governance
Delorean conducted its business activities during the quarter in accordance with its fundamental
commitment to sustainability under its ESG plan.
Delorean’s annual ESG report will provide stakeholders with a comprehensive analysis of the
Group’s Environmental, Social and Governance (ESG) performance, highlighting key sustainability
milestones achieved during the Financial Year. Additionally, it offers an update on the Company’s
continued progress towards future sustainability goals.
Planned Activity – Q1 FY2026
In Q1 FY2026, Delorean intends to focus in the following key areas:
•
•
•
•
•
•
•
•
Advancing the development of the NSW1 Bioenergy Project progressing toward a final
investment decision, with a focus on assessing project investment hurdles, securing longform offtake agreements, and negotiating joint venture and facility construction and
operation agreements. A final investment decision on project feasibility is expected to be
made by the board of directors of Brickworks and Delorean in 1HFY2026. While the
parties have agreed to continue to work together on this project, it is subject to Board
approval by each party and binding legal documentation being executed. There can be no
assurance that this project will proceed.
Continued construction of Delorean’s SA1 Project.
SA1 project contracted revenues in biomethane.
Delorean Engineering’s Yarra Valley Water project construction and commissioning
completion leading to first waste and gas enabling practical completion and move into
O&M.
Access debt funding from Tanarra Facility C
Secure funding for Delorean’s second shovel-ready project – the VIC1 project – to take the
project into construction alongside SA1.
Progress current grants processes applied for across the infrastructure projects
Progress the development of its QLD1 project.
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 30 JUNE 2025
8
Announcement
Delorean Corporation Chief Operating Officer, Neil Conquest, has released a short video
discussing this ASX Announcement on our interactive Investor Hub. Watch the video and
ask your questions here: https://investorhub.deloreancorporation.com.au/link/PbnL4P
Disclaimer
This report has been prepared by Delorean Corporation Limited (Delorean). The material
contained in this report is for information purposes only. This release is not an offer or invitation
for subscription or purchase of, or a recommendation in relation to, securities in Delorean and
neither this release nor anything contained in it shall form the basis of any contract or
commitment.
This report may contain forward-looking statements. Forward-looking statements include, but are
not limited to, statements concerning Delorean business plans, intentions, opportunities,
expectations, capabilities, and other statements that are not historical facts. Forward-looking
statements include those containing such words as could, plan, target, estimate, forecast,
anticipate, indicate, expect, intend, may, potential, should or similar expressions. Such forwardlooking statements are not guarantees of future performance and involve known and unknown
risks, uncertainties, assumptions, and other important factors, many of which are beyond the
control of Delorean, and which could cause actual results to differ from those expressed in this
report. Because actual results might differ materially to the information in this report, Delorean
does not make, and this report should not be relied upon as, any representation or warranty as to
the accuracy, or reasonableness, of the underlying assumptions and uncertainties. Investors are
cautioned to view all forward-looking statements with caution and to not place undue reliance on
such statements.
The report has been prepared by Delorean based on information available to it, including
information from third parties, and has not been independently verified. No representation or
warranty, express or implied, is made to the fairness, accuracy or completeness of the information
or opinions contained in this report.
About Delorean Corporation Ltd (ASX:DEL)
Shares in Delorean Corporation Limited (ASX: DEL) are traded on the Australian Securities
Exchange (ASX). For more information, please visit our website:
www.deloreancorporation.com.au