Q3 FY2025 Highlights
-
-
-
-
-
-
Snapshot: 2025 has begun as a landmark year as Delorean ramped up its transition to
renewable gas production and sustainable infrastructure ownership and operation. A
watershed moment and an Australian first was achieved when the Australian Gas
Infrastructure Group (AGIG) and Delorean jointly announced to connect Delorean’s SA1
Salisbury Bioenergy plant to the AGIG gas grid for the export and distribution of mains grade
renewable gas (biomethane). This followed the announcement of an agreement with
Supagas for the sale of biogenic food-grade liquid carbon dioxide (LCO2) from the SA1 plant.
Complimented by Delorean securing additional grant funding and further debt funding to
fully fund the upgraded SA1 project.
Cash Balance: $15.0 million as at 31 March 2025.
Receipts from Customers: $4.4 million for the quarter ended 31 March 2025.
Yarra Valley Water: Construction on site continued to advance on the $59.5 million Yarra
Valley Water food waste to energy Design Build Operate Maintain (DBOM) project. After the
completion of the major civil works on site, all inlet, outlet and digester tanks were
constructed. The reception building is completed, power generation and major process
equipment items have been delivered onsite and placed ready for mechanical and electrical
connection.
SA1 Project: During the quarter, further site teams mobilised to site and major earth works
commenced. All long lead items have been ordered with key suppliers, with the target of
reaching waste acceptance and first gas in FY2026.
Brickworks/NSW1 Project: Delorean continued to progress the ongoing co-development
of the NSW1 project, in its landmark collaboration with Brickworks Building Products. The
parties are actively working to set the timeline and path to Final Investment Decision (FID).
Corporate: The Company drew down $6.0 million from the Tanarra debt funding facility
during the quarter, to support the ongoing construction of the SA1 project. Since the
inception of the Tanarra facility to 31 March 2025, DEL has drawn a total of $23.85m.
Renewable Gas and CO2 Demand: Delorean demonstrated the significant ongoing and
growing demand for Delorean’s renewable natural gas (biomethane) and biogenic LCO2
through the announcement of the biomethane gas connection agreement with AGIG and the
sale agreement with Supagas for food grade biogenic LCO2 from the SA1 plant.
Image 1: YVW Bioenergy Project
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 31 MARCH 2025
2
Q3 FY2025 Activities Report
Delorean Corporation Limited (ASX: DEL) is pleased to provide an overview of the March
2025 quarter (Q3 FY2025) activities and the cash position.
Business Overview
Delorean Corporation is a vertically integrated business operating in two high growth investment
sectors – renewable energy and waste management. Delorean is leading the Australian market
with bioenergy and driving commercial production of mains-grade renewable gas. Delorean has
the inhouse capability to deliver bioenergy projects across the full lifecycle, from project
conception to completion; processing organic waste and generating and monetising renewable
electricity, heat and gas.
The core focus of the business is to develop, construct, own and operate bioenergy infrastructure
in Australia. Revenue is derived from the acceptance of organic waste and agricultural residues
(gate fees), the generation of renewable electricity and the production of renewable gas
(biomethane). Additional revenues are also available from the production of a bi-product,
renewable food grade liquid CO2 (biogenic LCO2) as well as Australian Carbon Credit Units
(ACCUs) and Renewable Gas Guarantees of Origin (RGGOs). Furthermore, there are prospects for
other revenue streams in the future, including the sale of liquid and solid biofertilisers. All these
monetisation streams contribute to the overall financial viability and sustainability of bioenergy
operations.
The business comprises three interoperable divisions:
•
Infrastructure (core): rollout of Delorean owned bioenergy infrastructure through our project
pipeline and key partnerships
•
Engineering: supporting the EPC and O&M of Delorean’s own projects, while selectively
supporting the Bioenergy sector with third party projects and partnerships
•
Energy Retail: retailing of renewable energy (electricity and gas) generated from Delorean
projects through our National electricity retail licence and Victorian Gas retail licence
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 31 MARCH 2025
3
Investment Highlights
Unique high yielding investment opportunity in the bioenergy sector
✓ Delorean is the only Build-Own-Operate (BOO) Bioenergy developer in Australia with a strong
track record of delivering successful award-winning projects across ANZ
✓ Delorean is uniquely positioned to develop its strategic portfolio of BOO projects with
significant industry partners
Long-term value upside
✓ High margin business with contracted multiple revenue flows – predictable and stable income
once assets are operational, underpinned by long-term contracts and attractive project
economics
✓ Unique proposition on the ASX providing equity exposure to shovel ready waste and clean
energy infrastructure projects that demonstrate significant project-level IRRs
Attractive industry dynamics with strong growth potential
✓ Bioenergy industry has significant ‘green’ tailwinds driven by demand for renewable energy
production and waste diversion
✓ Use of organic waste to create gas enables sale of gas at a ‘green’ premium and at a time of
significant undersupply
Project Pipeline
The following graphic sets out an overview of Delorean projects, completed, under construction,
under development and in the pipeline.
Delorean has successfully delivered 3 award-winning bioenergy projects (Jandakot WA, Blue Lake
Milling SA, Ecogas NZ) and is currently constructing its largest project to date for Yarra Valley Water
in Lilydale, Victoria, as well as its first Build-Own-Operate facility, the SA1 Salisbury Bioenergy in
South Australia. Delorean’s project pipeline will see Delorean delivering a greater number of
projects at a larger scale across Australia, consistent with the growth in the bioenergy sector.
Image 2: Delorean Corporation Project Portfolio
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 31 MARCH 2025
4
Delorean Engineering Division
Delorean’s Engineering Division delivers engineering design, construction and
operation/maintenance services for third parties under contract, and for Delorean Infrastructure
Division’s build/own/operate (BOO) projects.
During the quarter, Delorean’s Engineering Division was primarily focussed on:
•
Continued construction of Yarra Valley Water’s Lilydale facility. After the completion of the
major civil works on site, all inlet, outlet and digester tanks were constructed. The reception
building is completed, power generation and major process equipment items have been
delivered onsite and placed ready for mechanical and electrical connection.
•
Supporting the Brickworks (NSW1) Bioenergy project Development Application, led by the
Delorean Infrastructure Division.
•
Construction of SA1 with further site teams mobilised to site and major earth works
commenced. All long lead items have been procured with key suppliers, with the target of
reaching waste acceptance and first gas in FY2026.
•
Engineering Design and regulatory support for the Delorean infrastructure projects VIC1
and QLD1.
•
Operational support ongoing for Blue Lake Milling and Ecogas Bioenergy facilities
previously constructed by Delorean.
Yarra Valley Water, VIC Bioenergy Plant
Project Background
Location: Lilydale, Victoria – circa $59.5m total Design Build Operate Maintain (DBOM) contract
value
Project Update
Major Civil and Structural works on the Food Waste to Energy facility inclusive of earth works and
concrete works have been completed. The reception building, tanks and package equipment has
arrived on site and is in final stages of installation.
The site has completed over 40,000 hours without injury or lost time incidents (LTI’s).
Image 3: YVW Bioenergy Plant construction
Image 4: YVW Bioenergy Plant Render
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 31 MARCH 2025
5
Delorean Infrastructure Division
Delorean’s Infrastructure Division is responsible for development, ownership and operation of
commercial-scale anaerobic digestion bioenergy facilities in Australia.
During the quarter, Delorean’s Infrastructure Division was predominantly focussed on:
•
A gas connection agreement with Australian Gas Infrastructure Group (AGIG) to connect
Delorean’s SA1 Salisbury Bioenergy plant to the AGIG gas grid for the export and
distribution of mains grade renewable gas (biomethane).
•
An agreement with Supagas for the sale of food grade biogenic LCO2 from the SA1 plant.
•
Securing $6.1 million of grant funding from ARENA and $7.0 million of additional debt
funding from Tanarra to fully fund the upgraded SA1 project.
•
Continued progression with contracted revenues for SA1 with a focus on feedstock and
biomethane offtake. In addition to exploring opportunities in the biofertilizer sector for
digestate.
•
The Board continue to evaluate suitable opportunities to fund further projects in the
pipeline – including the other shovel ready project, VIC1 – and will seek to establish and
deliver on a strategy to fund the portfolio as a whole.
•
Investment due diligence and development activities on the VIC1 project.
•
Progressed the development of QLD1 project.
•
Ongoing development of Delorean’s infrastructure project portfolio.
SA1 Salisbury Bioenergy
Project Update
In December 2024, the Delorean Board reached Financial Investment Decision to proceed with
the construction of Delorean’s SA1 Bioenergy project in Edinburgh Parks, South Australia. The
project is now fully funded. Procurement of all long lead items have been ordered, and bulk earth
works have started.
Image 5: SA1 Salisbury Bioenergy Render
Image 6: SA1 Salisbury Bioenergy site works
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 31 MARCH 2025
6
NSW1 Brickworks Bioenergy
Project Update
In Q3 FY2025, Brickworks Building Products and Delorean continued to progress the
Development Stage of the NSW1 Bioenergy project under a Master Services Agreement (MSA).
The project has closed out the agency responses and made the formal submission for the
development approval, the focus is now on reaching FID.
Image 7 & 8: NSW1 Bioenergy Plant Render
VIC1 Stanhope Bioenergy
Delorean has commenced preliminary construction works, funded through working cashflows,
with the project and associated planning approvals remaining on foot. We are active in sourcing
finance to bring the project into full construction in parallel to the SA1 and pending NSW1 projects.
Image 9: VIC1 Bioenergy Plant Render
Delorean Infrastructure Project Portfolio Development
During Q3 FY2025, Delorean continued the active development of its bioenergy infrastructure
project pipeline. Beyond the SA1, VIC1 and NSW1 projects, the most advanced of these projects is
the QLD1 Bioenergy Plant. The Company is currently preparing to progress the QLD1 project from
feasibility stage to development approval. The project is expected to be FID-ready by late CY2025.
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 31 MARCH 2025
7
Delorean Energy Retail Division
Delorean’s Energy Retail Division is preparing for a strategic scale up of its retail operations as
Delorean’s Infrastructure assets come onstream. Delorean intends to retain its WA and National
retail electricity and Victorian Gas licenses on an ongoing basis in support of the Company’s rollout
of bioenergy infrastructure across Australia.
Delorean Corporate
Environment, Social and Governance
Delorean remains proud to be advancing its commitment to sustainability. In November 2024,
Delorean published its third annual ESG Report
Delorean’s ESG report provides stakeholders with a comprehensive analysis of the Group’s
Environmental, Social and Governance (ESG) performance, highlighting key sustainability
milestones achieved during the Financial Year. Additionally, it offers an update on the Company’s
continued progress towards future sustainability goals.
Planned Activity – Q4 FY2025
In Q4 FY2025, Delorean’s focus is in the following key areas:
•
•
•
•
•
•
•
•
Continued construction of Delorean’s SA1 Project.
Further focus on SA1 project contracted revenues in feedstock and biomethane.
Continuing the NSW1 project through the formal planning and development approval, and
continue to work on detailed commercial terms and project finance options with
Brickworks.
Delorean Engineering’s Yarra Valley Water project construction and commissioning
completion leading to first waste and gas enabling practical completion and move into
O&M.
Secure funding for Delorean’s second shovel-ready project – the VIC1 project – to take the
project into construction alongside SA1.
Business improvements through strengthened leadership, with a focus on cash flow and
BOO profitability.
Support current grants process applied for across the infrastructure projects nationally.
Progress the development of its QLD1 and WA2 projects.
Announcement
Delorean Corporation Chief Operating Officer, Neil Conquest, has released a short video
discussing this ASX Announcement on our interactive Investor Hub. Watch the video and
ask your questions here: https://investorhub.deloreancorporation.com.au/link/7PRW0y
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 31 MARCH 2025
8
Disclaimer
This report has been prepared by Delorean Corporation Limited (Delorean). The material
contained in this report is for information purposes only. This release is not an offer or invitation
for subscription or purchase of, or a recommendation in relation to, securities in Delorean and
neither this release nor anything contained in it shall form the basis of any contract or
commitment.
This report may contain forward-looking statements. Forward-looking statements include, but are
not limited to, statements concerning Delorean business plans, intentions, opportunities,
expectations, capabilities, and other statements that are not historical facts. Forward-looking
statements include those containing such words as could, plan, target, estimate, forecast,
anticipate, indicate, expect, intend, may, potential, should or similar expressions. Such forwardlooking statements are not guarantees of future performance and involve known and unknown
risks, uncertainties, assumptions, and other important factors, many of which are beyond the
control of Delorean, and which could cause actual results to differ from those expressed in this
report. Because actual results might differ materially to the information in this report, Delorean
does not make, and this report should not be relied upon as, any representation or warranty as to
the accuracy, or reasonableness, of the underlying assumptions and uncertainties. Investors are
cautioned to view all forward-looking statements with caution and to not place undue reliance on
such statements.
The report has been prepared by Delorean based on information available to it, including
information from third parties, and has not been independently verified. No representation or
warranty, express or implied, is made to the fairness, accuracy or completeness of the information
or opinions contained in this report.
About Delorean Corporation Ltd (ASX:DEL)
Shares in Delorean Corporation Limited (ASX: DEL) are traded on the Australian Securities
Exchange (ASX). For more information, please visit our website:
www.deloreancorporation.com.au
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 31 MARCH 2025
9
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 31 MARCH 2025
10
Share your feedback
Discover