25/05/2026
ASX Announcement
SA1 BUILD/OWN/OPERATE BIOENERGY FACILITY - CONSTRUCTION
UPDATE
HIGHLIGHTS:
• Construction of Delorean’s first 100%-owned SA1 Salisbury Bioenergy Facility is 75%
complete, with the project on track for acceptance of waste in August 2026 and first
renewable gas (biomethane) injection into the Adelaide gas network in November
2026.
• Construction activities continue to progress across multiple workstreams, with civil,
mechanical and site infrastructure works advancing towards completion.
• Strong safety performance maintained with zero lost time injuries recorded to date.
• GreenPower accreditation activities progressing to support renewable energy
certification pathway.
• The project will receive 70,000 tonnes per annum of organic waste from the Adelaide
metro area and produce 210 TJ per annum of renewable gas and 6,000 tonnes per
annum of biogenic food grade liquid CO2.
• SA1 is a template project for the rollout of Delorean’s shovel-ready and near-term
infrastructure project portfolio, with NSW1 and VIC1 facilities expected to enter
construction in CY2026.
Delorean Corporation Limited (ASX: DEL) (“Delorean” or “the Company”) is pleased to
provide an investor update specifically focussed on progress and status of its 100%-
owned SA1 Salisbury bioenergy facility in Edinburgh Parks, South Australia as a
template for the Company’s rollout of its pipeline of shovel-ready and near-term
projects.
Snapshot of Delorean’s SA1 Bioenergy Facility
SA1 is Delorean’s first 100%-owned bioenergy infrastructure project, headlining the rollout
of a further four shovel-ready and near-term build/own/operate facilities across Australia.
Construction of Delorean’s first 100%-owned SA1 Facility is 75% complete, and on track
for completion for acceptance of waste in August 2026 and first renewable gas
(biomethane) injection into the Adelaide gas network in November 2026.
Delorean’s construction of this project builds on its established track record having built
four award-winning commercial-scale facilities of equivalent capacity for third parties in
Delorean Corporation Ltd | ACN 638 111 127
Deloreancorporation.com.au |Unit 1 Ground Floor, 1205 Hay Street WEST PERTH WA 6005 | PH: 08 6147 7575
Australia and New Zealand since 2014, most recently for Yarra Valley Water in Victoria,
that Delorean is currently operating.
The SA1 project will process 70,000 tonnes per annum of organic waste from the
commercial, industrial and municipal sectors in Adelaide’s metro area using anaerobic
digestion to produce 210 TJ per annum of renewable gas and 6,000 tonnes per annum of
`biogenic food grade liquid CO2. In addition, the facility will generate valuable
environmental credits in the form of Australian Carbon Credit Units (ACCU’s) and
Renewable Gas Guarantee of Origin (RGGO) Certificates and a biofertiliser product with
upside opportunities in an emerging agricultural market.
On commissioning, the facility will export biomethane into the Adelaide gas network under
a long-term offtake to Origin Energy for use by industrial customers. It will be the first
facility in Australia to export biomethane into the gas network from processing commercial
and industrial organic waste streams.
SA1 Construction Status Update
A summary of construction status is set out below:
• All major equipment has been ordered and the majority delivered to site.
• Construction activities continue to progress across multiple workstreams, with civil,
mechanical and site infrastructure works advancing towards completion.
• Civil works are substantially completed, with asphalt completed and structural
foundations largely advanced across the site.
• Major process and mechanical equipment has been installed, including key pre-
treatment and compression systems, with additional equipment currently in transit to
site.
• Site building and infrastructure works are progressing, with cladding and weighbridge
installation about to commence, and additional finishing and fit-out works scheduled to
follow.
• Electrical installation is scheduled to commence in mid-June, alongside the installation
SA1 Salisbury Bioenergy render SA1 Salisbury Bioenergy construction
Delorean Corporation Ltd | ACN 638 111 127
Deloreancorporation.com.au |Unit 1 Ground Floor, 1205 Hay Street WEST PERTH WA 6005 | PH: 08 6147 7575
of remaining equipment including the flare, booster, LCO₂ system, and BMU blower.
• The Low-Pressure Injection Skid is ready for delivery to site, enabling biomethane
injection from the SA1 facility into the Australian Gas Infrastructure Group (AGIG) gas
distribution network in South Australia.
• Strong safety performance maintained with zero lost time injuries recorded to date.
• GreenPower accreditation activities progressing to support renewable energy
certification pathway.
SA1 Salisbury Bioenergy construction
Delorean Managing Director Joe Oliver inspecting Low-Pressure
Injection Skid works
Reception Shed cladding materials arriving onsite for installation
Weighbridge installation works progressing on site Asphalting completed across site, including visitor car bays
SA1 site works progressing
Delorean Corporation Ltd | ACN 638 111 127
Deloreancorporation.com.au |Unit 1 Ground Floor, 1205 Hay Street WEST PERTH WA 6005 | PH: 08 6147 7575
Delorean Investor Site Tour
On Friday, 22 May, Delorean Corporation hosted an investor site tour of its flagship SA1
Salisbury Bioenergy Facility construction site, providing attendees with a first-hand view of
construction progress and an opportunity to experience the scale and impact of Delorean’s
operations, including the delivery of South Australia’s first food-waste-to-renewable-gas
project.
SA1 Facility A Template for Delorean’s Infrastructure Portfolio
The SA1 Facility is a template for the roll out of Delorean’s shovel-ready and near term
infrastructure project pipeline, in terms of capacity and scale, organic feedstocks, volume of
biomethane and liquid CO2 production, and generation of ACCU’s and RGGO’s, as well as
production of biofertiliser.
Announcement Video
Delorean Corporation Managing Director Joe Oliver has released a short video
discussing this ASX Announcement on our interactive Investor Hub. Watch the video and
ask your questions here: https://investorhub.deloreancorporation.com.au/link/ya2vle
Installation of reception shed roller doors completed Reception shed being prepared for cladding
SA1 Site Tour SA1 Site Tour
Delorean Corporation Ltd | ACN 638 111 127
Deloreancorporation.com.au |Unit 1 Ground Floor, 1205 Hay Street WEST PERTH WA 6005 | PH: 08 6147 7575
Authorised on behalf of the Delorean Corporation Board of Directors by Hamish Jolly,
Executive Chair.
For more information/interview please contact:
Joe Oliver, Managing Director
Delorean Corporation Ltd
+61 (0) 8 6147 7575
info@deloreancorporation.com.au
About Delorean Corporation Limited
Delorean Corporation is a leading Australian bioenergy company. Delorean
specialises in the design, build, ownership and management of bioenergy
infrastructure. Delorean Corporation is a vertically integrated company positioned in
two high growth industries; renewable energy and waste management.
Delorean Corporation comprises an Engineering Division, Infrastructure Division and
Energy Retail Division. Through these divisions Delorean Corporation has the inhouse
capability to deliver bioenergy projects across the full lifecycle, from project conception to
completion, processing organic waste, generating renewable energy and monetising the sale
of green electricity, heat and gas.
DEL’s projects produce renewable energy whilst reducing the volume of waste going to
landfill, utilising a model that generates multiple revenue streams.
For more Company information and to engage with management by asking questions about
Delorean's latest announcements and updates, visit
https://investorhub.deloreancorporation.com.au/
SA1 Edinburgh Parks Bioenergy Plant
The SA1 Salisbury Bioenergy plant is 100% Delorean Corporation owned and strategically
located in the Northern Adelaide Food Park in Edinburgh Parks (metropolitan Adelaide) in
South Australia on land owned by Delorean. The project is currently in construction.
Stage 1 of the project will process 70,000 tonnes per annum of organic waste streams for the
nominal production of up to 210 TJ per annum of renewable natural gas (biomethane)
exported to the Adelaide’s Gas network, under a gas offtake agreement to Australian Gas
Infrastructure Group (“AGIG”).
In Stage 2 (future expansion), there is the potential for extension to 125,000 tonnes per
annum under the current development approval. The SA1 Project will produce 6 different
products and revenue streams, including Renewable Natural Gas (Biogenic Methane),
renewable food grade liquid CO2 (Biogenic LCO2), Carbon Credits (ACCUs), Renewable Gas
Guarantees of Origin (RGGOs), Liquid Fertilisers and Gate Fees.