Delorean Company Update - September 2024 Quarter
Released
Released
Announcement PDF
Australia’s future in bioenergy and renewables
Company
Update
for the quarter ended
30 September 2024
2024
Delorean Corporation Limited
ACN 638 111 127
Q1 FY2025 Highlights
-
-
-
-
-
-
Snapshot: Delorean is going from strength to strength at the start of FY2025, following its
record profits posted in FY2024. The company has executed a funding agreement with
Tanarra Restructuring Partners for the provision of a 3-year term corporate finance
facility package of up to $30m, to fund Delorean’s first build, own, operate bioenergy
project.
Cash Balance: Current cash balance of $8m as at 30 September 2024.
Receipts from Customers: $7.99M for the quarter ended 30 September 2024
Yarra Valley Water: In Q1 FY2025, construction works continued on the $53m Yarra
Valley Water food waste to energy project with tank construction underway, delivery of
major plant items to site and significant progress on civils delivery.
SA1 Project: During the quarter, Delorean engaged in active preparation of the SA1
Project for construction, with $25m of the Tanarra facility assigned to this project. The
Company is presently finalising the delivery team, key suppliers and project program, with
the aim of reaching Final Investment Decision (FID) in Q2 FY2025.
Brickworks/NSW1 Project: The ongoing co-development of the NSW1 project, in a
landmark collaboration with Brickworks Building Products, continues to progress, with
the public exhibition phase for development approval now complete, and the parties
actively working to set the timeline and path to FID for the project.
Corporate: The Company received the first $5m from the Tanarra facility during
September 2024, with these funds facilitating early redemption of Palisade Impact’s
Convertible Notes in full. Delorean now holds no convertible debt.
Renewable Gas Demand: Significant ongoing demand from both government and
business sectors for Delorean’s renewable natural gas (biomethane) product in a market
where renewable gas is scarce.
Image 1: YVW Bioenergy Project construction
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 30 SEPTEMBER 2024
2
Q1 FY2025 Activities Report
Delorean Corporation Limited (ASX:DEL) is pleased to provide an overview of the
September 2024 quarter (Q1 FY2025) activities and the associated cash flows and cash
position.
Business Overview
Delorean Corporation is a vertically integrated business operating in two high growth investment
sectors – renewable energy and waste management. Delorean is leading the Australian market
with bioenergy and driving commercial production of mains-grade renewable gas. Delorean has
the inhouse capability to deliver bioenergy projects across the full lifecycle, from project
conception to completion; processing organic waste and generating and monetising renewable
electricity, heat and gas.
The core focus of the business is to develop, construct, own and operate bioenergy infrastructure
in Australia. Revenue is derived from the acceptance of organic waste and agricultural residues,
the generation of renewable electricity and the production of renewable natural gas. Furthermore,
there are prospects for additional revenue streams in the future, including the sale of biofertiliser,
CO2, hydrogen and environmental credits. These opportunities contribute to the overall financial
viability and sustainability of bioenergy operations.
The business comprises three interoperable divisions:
•
Infrastructure (core): rollout of Delorean owned bioenergy projects through partnerships
•
Engineering: supporting the EPC and O&M of Delorean’s own projects, while selectively taking
on third-party work
•
Energy Retail: Retailing of energy (electricity and gas) generated solely from Delorean projects
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 30 SEPTEMBER 2024
3
Investment Highlights
Unique high yielding investment opportunity in the bioenergy sector
✓ Delorean is the only Build-Own-Operate (BOO) Bioenergy developer in Australia with a strong
track record of delivering successful projects in ANZ
✓ Delorean is uniquely positioned to develop its strategic portfolio of BOO projects with
significant industry partners
Long-term value upside
✓ High margin business with contracted revenue flows – predictable and stable income once
assets are operational, underpinned by long-term contracts and attractive project economics
✓ Unique proposition on the ASX providing equity exposure to shovel ready projects that
demonstrate significant project-level IRRs
Attractive industry dynamics with strong growth potential
✓ Bioenergy industry has significant ‘green’ tailwinds driven by demand for renewable energy
production and waste diversion
✓ Use of organic waste to create gas enables sale of gas at a ‘green’ premium and at a time of
significant undersupply
Project Pipeline
The following graphic sets out an overview of Delorean projects, completed, under construction,
under development and in the pipeline.
Delorean has successfully delivered 3 award-winning bioenergy projects (Jandakot WA, Blue Lake
Milling SA, Ecogas NZ) and is now in construction of its fourth and biggest project for Yarra Valley
Water. Delorean’s project pipeline will see Delorean delivering a greater number of projects at a
larger scale across Australia, consistent with the growth in the bioenergy sector.
Image 2: Delorean Corporation Project Portfolio
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 30 SEPTEMBER 2024
4
Delorean Engineering Division
Delorean’s Engineering Division delivers engineering design, construction and
operation/maintenance services for third parties under contract, and for Delorean Infrastructure
Division’s build/own/operate projects.
During the quarter, Delorean’s Engineering Division was primarily focussed on:
•
Construction of Yarra Valley Water’s Lilydale facility, with delivery of major plant items,
AD tanks and receivable shed being constructed.
•
Supporting the engineering design and submission of the Brickworks (NSW1) Bioenergy
project Development Application, led by the Delorean Infrastructure Division.
•
Final preparations for SA1 construction are being made, with supplier negotiations
underway, an early works package prepared to clear the site, and the key appointments
for the project delivery team completed.
•
Engineering Design and regulatory support for the Delorean infrastructure projects VIC1,
QLD1 and WA2.
•
Operational support ongoing for Blue Lake Milling and Ecogas Bioenergy facilities
previously constructed by Delorean.
Yarra Valley Water, VIC Bioenergy Plant
Project Background
Location: Lilydale, Victoria – circa $53m + $6.5m O&M contract value
Project Update
Bulk earthworks on the Waste to Energy facility and access road have been completed. Concrete
works have been completed on the Tank Farm and Heavy Vehicle Pavement. The Reception Shed
and equipment has arrived at site with installation ongoing.
Image 3 - 5: Yarra Valley Water construction
Image 6: Yarra Valley Water food waste to energy plant render
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 30 SEPTEMBER 2024
5
Delorean Infrastructure Division
Delorean’s Infrastructure Division is responsible for development, ownership and operation of
commercial-scale anaerobic digestion bioenergy facilities in Australia.
During the quarter, Delorean’s Infrastructure Division was predominantly focussed on:
•
Completing submission of Environmental Impact Statements and Development
Application for the Brickworks Project (NSW1).
•
In September 2024, Delorean executed contracts with Tanarra Group for a $30m
corporate debt facility, with $25m from that facility allocated to development of DEL’s first
build, own, operate project: SA1.
•
The Board continue to evaluate suitable opportunities to fund further projects in the
pipeline – including the other shovel ready project, VIC1 – and will seek to establish and
deliver on a strategy to fund the portfolio as a whole.
•
Investment due diligence and development activities on the Company’s VIC1 and SA1
projects.
•
Progressed the development of QLD1 and WA2 projects.
•
Ongoing development of Delorean’s infrastructure project portfolio.
Brickworks Bioenergy Project Development
Project Update
In Q1 FY2025, Brickworks Building Products and Delorean continued to progress the
Development Stage of the NSW1 project under a Master Services Agreement (MSA). In Q1,
FY2025, the project reached a significant milestone with the public exhibition of the EIS for the
development approval now complete. Delorean is completing the responses to agency
submissions, ready for full submission in Q2 of FY2025.
Image 7 & 8: NSW1 Bioenergy Plant Render
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 30 SEPTEMBER 2024
6
SA1 Project Development
In September 2024, Delorean executed contracts with Tanarra Group for a debt funding facility,
which provides $25m for construction of the SA1 Project. With investor due diligence completed
and all conditions satisfied, the Company is preparing the project for Final Investment Decision,
expected in Q2 FY2025.
Image 9: SA1 Bioenergy Plant Render
VIC1 Project
Following the agreement for the debt facility from Tanarra for the SA1 Project, Delorean’s focus
for this quarter and beyond is to secure a complementary investment partner for the VIC1 project,
which will enable the company to fast-track the start of construction on this project, being the
second of the Company’s build, own, operate project portfolio. VIC1 is shovel ready for full
construction pending project finance.
Image 10: VIC1 Bioenergy Plant Render
Delorean Infrastructure Project Pipeline Development
During Q1 FY2025, Delorean continued the active development of its bioenergy infrastructure
project pipeline. Beyond the SA1, VIC1 and NSW1 projects, the most advanced of these projects is
the QLD1 Bioenergy Plant. The Company is currently preparing to progress the QLD1 project from
feasibility stage to development approval. The project is expected to be FID-ready by late FY2025.
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 30 SEPTEMBER 2024
7
Delorean Energy Retail Division
Delorean’s Energy Retail Division is preparing for a strategic scale up of its retail operations as
Delorean’s Infrastructure assets come onstream. Delorean intends to retain its WA and National
retail electricity and Victorian Gas licenses on an ongoing basis in support of the Company’s rollout
of bioenergy infrastructure across Australia.
Delorean Corporate
Environment, Social and Governance
Delorean remains proud to be advancing its commitment to sustainability. In November 2024,
Delorean published its third annual ESG Report.
Delorean’s ESG report provides stakeholders with a comprehensive analysis of the Group’s
Environmental, Social and Governance (ESG) performance, highlighting key sustainability
milestones achieved during the Financial Year. Additionally, it offers an update on the Company’s
continued progress towards future sustainability goals.
Planned Activity – Q2 FY2025
In Q2 FY2025, Delorean’s focus is in the following key areas:
•
•
•
•
•
•
Move Delorean’s SA1 Project into construction after reaching internal FID.
Progress and support the NSW1 project through the formal planning and development
approval submission, and work on detailed commercial terms and project finance options
with Brickworks.
Continue to successfully deliver and progress the Delorean Engineering’s Yarra Valley
Water project, on time and budget.
Business improvements through strengthened leadership team with a focus on cash flow
and profitability.
Support current grants process applied for across the infrastructure projects nationally.
Progress the development of its QLD1 and WA2 projects.
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 30 SEPTEMBER 2024
8
Disclaimer
This report has been prepared by Delorean Corporation Limited (Delorean). The material
contained in this report is for information purposes only. This release is not an offer or invitation
for subscription or purchase of, or a recommendation in relation to, securities in Delorean and
neither this release nor anything contained in it shall form the basis of any contract or
commitment.
This report may contain forward-looking statements. Forward-looking statements include, but are
not limited to, statements concerning Delorean business plans, intentions, opportunities,
expectations, capabilities, and other statements that are not historical facts. Forward-looking
statements include those containing such words as could, plan, target, estimate, forecast,
anticipate, indicate, expect, intend, may, potential, should or similar expressions. Such forwardlooking statements are not guarantees of future performance and involve known and unknown
risks, uncertainties, assumptions, and other important factors, many of which are beyond the
control of Delorean, and which could cause actual results to differ from those expressed in this
report. Because actual results might differ materially to the information in this report, Delorean
does not make, and this report should not be relied upon as, any representation or warranty as to
the accuracy, or reasonableness, of the underlying assumptions and uncertainties. Investors are
cautioned to view all forward-looking statements with caution and to not place undue reliance on
such statements.
The report has been prepared by Delorean based on information available to it, including
information from third parties, and has not been independently verified. No representation or
warranty, express or implied, is made to the fairness, accuracy or completeness of the information
or opinions contained in this report.
About Delorean Corporation Ltd (ASX:DEL)
Shares in Delorean Corporation Limited (ASX: DEL) are traded on the Australian Securities
Exchange (ASX). For more information, please visit our website: