December 2024 Quarterly Activities Report
Released
Released
Announcement PDF
Australia’s future in bioenergy and renewables
Company
Update
for the quarter ended
31 December 2024
2024
Delorean Corporation Limited
ACN 638 111 127
Q2 FY2025 Highlights
-
-
-
-
-
-
Snapshot: Delorean continued its growth trajectory in the second quarter of FY2025.
Focussed on transitioning to infrastructure ownership, Delorean reached a key pivot point
in December 2024 with internal Financial Investment Decision (FID) on the 100%-owned
Build Own Operate (BOO) SA1 Bioenergy Project, with the further development of
Delorean’s BOO Project portfolio and good progress on the current Yarra Valley Water
project build.
Cash Balance: Current cash balance of $15.3m as at 31 December 2024.
Receipts from Customers: $7.59M for the quarter ended 31 December 2024.
Yarra Valley Water: In Q2 FY2025, construction works continued on the $53m Yarra Valley
Water food waste to energy project. After the completion of the major civil works on site,
tank construction was completed on the inlet and outlet tanks and digesters. The reception
building is well underway and major plant and equipment items have been delivered onsite
and placed ready for mechanical and electrical connection.
SA1 Project: During the quarter, Delorean reached internal FID, mobilised the site and the
key project team, procured the majority of the long lead items from the Company’s approved
key suppliers, with the aim of reaching waste acceptance by Q2 FY2026 and First Gas by Q3
FY2026.
Brickworks/NSW1 Project: Delorean continued to progress the ongoing co-development
of the NSW1 project, in its landmark collaboration with Brickworks Building Products. The
public exhibition phase for development approval has been completed, with public
submissions received and responses being finalised. The parties are actively working to set
the timeline and path to FID for the project expected late Q4 FY2025.
Corporate: The Company drew down $12.85m from the Tanarra funding facility during the
quarter to December 2024, to support the start of construction and order of long lead items
of the SA1 Project. Since the inception of the Tanarra Facility to date, DEL has drawn a total
of $17.85m. Also in the period, the Company settled its historical loan with Roadnight Capital
in full.
Renewable Gas and CO2 Demand: Significant ongoing demand from both government and
business sectors for Delorean’s renewable natural gas (biomethane) and biogenic CO2
product in a market where renewable gas is scarce.
Image 2: SA1 Bioenergy Project site works
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 31 DECEMBER 2024
2
Q2 FY2025 Activities Report
Delorean Corporation Limited (ASX:DEL) is pleased to provide an overview of the
December 2024 quarter (Q2 FY2025) activities and the associated cash flows and cash
position.
Business Overview
Delorean Corporation is a vertically integrated business operating in two high growth investment
sectors – renewable energy and waste management. Delorean is leading the Australian market
with bioenergy and driving commercial production of mains-grade renewable gas. Delorean has
the inhouse capability to deliver bioenergy projects across the full lifecycle, from project
conception to completion; processing organic waste and generating and monetising renewable
electricity, heat and gas.
The core focus of the business is to develop, construct, own and operate bioenergy infrastructure
in Australia. Revenue is derived from the acceptance of organic waste and agricultural residues,
the generation of renewable electricity and the production of renewable natural gas. Furthermore,
there are prospects for additional revenue streams in the future, including the sale of biofertiliser,
CO2, and environmental credits. These opportunities contribute to the overall financial viability
and sustainability of bioenergy operations.
The business comprises three interoperable divisions:
•
Infrastructure (core): rollout of Delorean owned bioenergy infrastructure through our project
pipeline and key partnerships
•
Engineering: supporting the EPC and O&M of Delorean’s own projects, while selectively
supporting the Bioenergy sector with third party projects and partnerships
•
Energy Retail: Retailing of renewable energy (electricity and gas) generated from Delorean
projects through our National electricity retail licence and Victorian Gas retail licence
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 31 DECEMBER 2024
3
Investment Highlights
Unique high yielding investment opportunity in the bioenergy sector
✓ Delorean is the only Build-Own-Operate (BOO) Bioenergy developer in Australia with a strong
track record of delivering successful award-winning projects across ANZ
✓ Delorean is uniquely positioned to develop its strategic portfolio of BOO projects with
significant industry partners
Long-term value upside
✓ High margin business with contracted revenue flows – predictable and stable income once
assets are operational, underpinned by long-term contracts and attractive project economics
✓ Unique proposition on the ASX providing equity exposure to shovel ready waste and energy
infrastructure projects that demonstrate significant project-level IRRs
Attractive industry dynamics with strong growth potential
✓ Bioenergy industry has significant ‘green’ tailwinds driven by demand for renewable energy
production and waste diversion
✓ Use of organic waste to create gas enables sale of gas at a ‘green’ premium and at a time of
significant undersupply
Project Pipeline
The following graphic sets out an overview of Delorean projects, completed, under construction,
under development and in the pipeline.
Delorean has successfully delivered 3 award-winning bioenergy projects (Jandakot WA, Blue Lake
Milling SA, Ecogas NZ) and is now in construction of its fourth and biggest project for Yarra Valley
Water. Delorean’s project pipeline will see Delorean delivering a greater number of projects at a
larger scale across Australia, consistent with the growth in the bioenergy sector.
Image 2: Delorean Corporation Project Portfolio
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 31 DECEMBER 2024
4
Delorean Engineering Division
Delorean’s Engineering Division delivers engineering design, construction and
operation/maintenance services for third parties under contract, and for Delorean Infrastructure
Division’s build/own/operate projects.
During the quarter, Delorean’s Engineering Division was primarily focussed on:
•
Continued construction of Yarra Valley Water’s Lilydale facility, with delivery of major plant
items, AD tanks, process equipment and receivable shed underway.
•
Supporting the engineering design and submission of the Brickworks (NSW1) Bioenergy
project Development Application, led by the Delorean Infrastructure Division.
•
Construction of SA1 having started, with project delivery team are in place and mobilised
on site.
•
Engineering Design and regulatory support for the Delorean infrastructure projects VIC1
and QLD1.
•
Operational support ongoing for Blue Lake Milling and Ecogas Bioenergy facilities
previously constructed by Delorean.
Yarra Valley Water, VIC Bioenergy Plant
Project Background
Location: Lilydale, Victoria – circa $53m + $6.5m O&M contract value
Project Update
Major Civil works on the Food Waste to Energy facility inclusive of earth works and concrete works
have been completed. The reception building, tanks and package equipment has arrived on site
and being placed ready for connection with installation ongoing.
The site has completed over 30,587 hours without injury or lost time incidents (LTI’s) and
completed an ISO Quality and Safety audit with success.
Image 3 - 5: YVW Bioenergy Plant construction
Image 6: YVW Bioenergy Plant Render
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 31 DECEMBER 2024
5
Delorean Infrastructure Division
Delorean’s Infrastructure Division is responsible for development, ownership and operation of
commercial-scale anaerobic digestion bioenergy facilities in Australia.
During the quarter, Delorean’s Infrastructure Division was predominantly focussed on:
•
Completing submission of Environmental Impact Statements and Development
Application for the Brickworks Project (NSW1).
•
In September 2024, Delorean executed contracts with Tanarra Group for a $30m
corporate debt facility, with $25m from that facility allocated to development of DEL’s first
build, own, operate project: SA1.
•
Continued progression with contracted revenues for SA1 with a focus on feedstock,
biomethane offtake and CO2. In addition to exploring opportunities in the biofertilizer
sector for digestate.
•
The Board continue to evaluate suitable opportunities to fund further projects in the
pipeline – including the other shovel ready project, VIC1 – and will seek to establish and
deliver on a strategy to fund the portfolio as a whole.
•
Investment due diligence and development activities on the VIC1 project.
•
Progressed the development of QLD1 project.
•
Ongoing development of Delorean’s infrastructure project portfolio.
SA1 Project Development
In December 2024, the Delorean Board reached Financial Investment Decision to proceed with the
construction of Delorean’s SA1 bioenergy project in Edinburgh Parks, South Australia. Procurement of
all long lead items has progressed, and site works have begun.
Image 7: SA1 Bioenergy Plant Render
Image 8-9: SA1 Bioenergy Project Site
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 31 DECEMBER 2024
6
Brickworks Bioenergy Project Development
Project Update
In Q1 FY2025, Brickworks Building Products and Delorean continued to progress the
Development Stage of the NSW1 project under a Master Services Agreement (MSA). In Q2,
FY2025, the project closed out the agency responses ready for submission for the development
approval, and a focus of reaching FID by late Q4 2025.
Image 10 & 11: NSW1 Bioenergy Plant Render
VIC1 Project
Following the agreement for the debt facility from Tanarra for the SA1 Project, Delorean’s focus
for this quarter continued to be securing a complementary investment/finance partner for the
VIC1 project, which will enable the company to fast-track the start of construction on this project,
being the second of the Company’s build, own, operate project portfolio. VIC1 is shovel ready for
full construction pending project finance.
Image 12: VIC1 Bioenergy Plant Render
Delorean Infrastructure Project Pipeline Development
During Q2 FY2025, Delorean continued the active development of its bioenergy infrastructure
project pipeline. Beyond the SA1, VIC1 and NSW1 projects, the most advanced of these projects is
the QLD1 Bioenergy Plant. The Company is currently preparing to progress the QLD1 project from
feasibility stage to development approval. The project is expected to be FID-ready by late CY2025.
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 31 DECEMBER 2024
7
Delorean Energy Retail Division
Delorean’s Energy Retail Division is preparing for a strategic scale up of its retail operations as
Delorean’s Infrastructure assets come onstream. Delorean intends to retain its WA and National
retail electricity and Victorian Gas licenses on an ongoing basis in support of the Company’s rollout
of bioenergy infrastructure across Australia.
Delorean Corporate
Environment, Social and Governance
Delorean remains proud to be advancing its commitment to sustainability. In November 2024,
Delorean published its third annual ESG Report.
Delorean’s ESG report provides stakeholders with a comprehensive analysis of the Group’s
Environmental, Social and Governance (ESG) performance, highlighting key sustainability
milestones achieved during the Financial Year. Additionally, it offers an update on the Company’s
continued progress towards future sustainability goals.
Planned Activity – Q3 FY2025
In Q3 FY2025, Delorean’s focus is in the following key areas:
•
•
•
•
•
•
•
•
Successful delivery and construction of Delorean’s SA1 Project after reaching internal FID.
Further focus of SA1 project contracted revenues in feedstock, biomethane and biogenic
CO2 offtakes.
Submission of the NSW1 project through the formal planning and development approval,
and work on detailed commercial terms and project finance options with Brickworks.
Continue to successfully deliver and progress the Delorean Engineering’s Yarra Valley
Water project, on time and budget.
Secure funding for Delorean’s second shovel-ready project – the VIC1 project – to take the
project into construction alongside SA1.
Business improvements through strengthened leadership, with a focus on cash flow and
profitability.
Support current grants process applied for across the infrastructure projects nationally.
Progress the development of its QLD1 and WA2 projects.
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 31 DECEMBER 2024
8
Disclaimer
This report has been prepared by Delorean Corporation Limited (Delorean). The material
contained in this report is for information purposes only. This release is not an offer or invitation
for subscription or purchase of, or a recommendation in relation to, securities in Delorean and
neither this release nor anything contained in it shall form the basis of any contract or
commitment.
This report may contain forward-looking statements. Forward-looking statements include, but are
not limited to, statements concerning Delorean business plans, intentions, opportunities,
expectations, capabilities, and other statements that are not historical facts. Forward-looking
statements include those containing such words as could, plan, target, estimate, forecast,
anticipate, indicate, expect, intend, may, potential, should or similar expressions. Such forwardlooking statements are not guarantees of future performance and involve known and unknown
risks, uncertainties, assumptions, and other important factors, many of which are beyond the
control of Delorean, and which could cause actual results to differ from those expressed in this
report. Because actual results might differ materially to the information in this report, Delorean
does not make, and this report should not be relied upon as, any representation or warranty as to
the accuracy, or reasonableness, of the underlying assumptions and uncertainties. Investors are
cautioned to view all forward-looking statements with caution and to not place undue reliance on
such statements.
The report has been prepared by Delorean based on information available to it, including
information from third parties, and has not been independently verified. No representation or
warranty, express or implied, is made to the fairness, accuracy or completeness of the information
or opinions contained in this report.
About Delorean Corporation Ltd (ASX:DEL)
Shares in Delorean Corporation Limited (ASX: DEL) are traded on the Australian Securities
Exchange (ASX). For more information, please visit our website:
www.deloreancorporation.com.au
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 31 DECEMBER 2024
9
DELOREAN CORPORATION LIMITED | COMPANY ACTIVITIES REPORT 31 DECEMBER 2024
10
Share your feedback
Discover